Migration timeline
- May 2, 2025 -- Stop all activities on Alma and Primo VE PROD
- May 23, 2025 -- INN-Reach Freeze
- June 10, 2025 -- Sierra Fulfillment Freeze. ILS OPAC read-only
- June 11, 2025 -- Delivery of Alma production with Cutover data
- June 13, 2025 -- Provide written data acceptance of migrated data in Alma
- June 14 - 22, 2025 -- Alma data cleanup, excepting Patrons and Fulfillment
- June 18-19, 2025 -- Load patrons, loans, fines/fees and requests to Alma [EXL]
- June 20, 2025 -- Provide written acceptance of Fulfillment data AND Alma environment
- June 23, 2025 -- Final Go-Live Processes Run/Enabled [EXL]